watermark
Table 5.5.18—Industry investigation zone
Use
Categories of development and assessment
Assessment benchmarks
Accepted development
Development approval is not required
Not applicable
Accepted development, subject to compliance with identified requirements
If complying with all acceptable outcomes in section A of the Rural activities code
Not applicable
Assessable development—Code assessment
If not complying with all acceptable outcomes in section A of the Rural activities code
Rural activities code—purpose, overall outcomes and section A outcomes only
Accepted development
If for a cattery for 10 or fewer cats or a kennel for 4 or fewer dogs
Not applicable
Assessable development—Code assessment
If not for a cattery for 10 or fewer cats or a kennel for 4 or fewer dogs
Assessable development—Code assessment
-
Accepted development, subject to compliance with identified requirements
If complying with all acceptable outcomes in the Caretaker’s accommodation code
Not applicable
Assessable development—Code assessment
If not complying with all acceptable outcomes in the Caretaker’s accommodation code
Accepted development, subject to compliance with identified requirements
If complying with all acceptable outcomes in section A of the Rural activities code
Not applicable
Assessable development—Code assessment
If not complying with all acceptable outcomes in section A of the Rural activities code
Rural activities code—purpose, overall outcomes and section A outcomes only
Assessable development—Code assessment
-
Accepted development, subject to compliance with identified requirements
If complying with all acceptable outcomes in the Park code
Not applicable
Assessable development—Code assessment
If not complying with all acceptable outcomes in the Park code
Telecommunications facility where not a broadcasting station or television station
Assessable development—Code assessment
If not accepted development in section 5.3.4
Prescribed secondary code
Utility installation where sewage pump station, water pump station or water reservoir
Accepted development, subject to compliance with identified requirements
If involving a new premises or an existing premises with an increase in gross floor area, where complying with all acceptable outcomes in section A of the Special purpose code
Not applicable
Assessable development—Code assessment
If involving a new premises or an existing premises with an increase in gross floor area, where not complying with all acceptable outcomes in section A of the Special purpose code
Special purpose code—purpose, overall outcomes and section A outcomes only
Utility installation where not sewage pump station, water pump station or water reservoir
Assessable development—Code assessment
-
Assessable development—Impact assessment
Any other use not listed in this table.
Any use listed in this table and not meeting the description listed in the "Categories of development and assessment" column.
Any other undefined use.
The planning scheme

Note—Prescribed accepted development that is not assessable under the planning scheme is identified in section 5.3.4.

Editor’s note—The above categories of development and assessment apply unless otherwise prescribed in the Regulation.

Editor’s note—The default category of assessment is impact assessment unless otherwise prescribed in the Regulation.

^ Back to Top